Key points
- The QBCC's New Home Construction Contract sets default stages after a 5% deposit: Base 15%, Frame 20%, Enclosed 25%, Fixing 20% and Practical Completion 15%, and the parties can choose different stages instead.
- Under that contract the owner checks each progress claim before practical completion and pays a valid one within 5 business days of receipt, or gives a written notice of dispute in the same window; the practical completion claim is payable as soon as the builder meets the handover requirements.
- During the build you usually pay interest only on the amount drawn so far, so repayments start small and rise with each drawdown, then switch to principal and interest at the end.
- Some lenders, ANZ among them, use your own cash contribution before the first drawdown; lenders may inspect or value the work before releasing funds; and before the final payment NAB asks for an occupancy certificate and ANZ must confirm the home is insured.
- Through a lender, the Queensland first home owner grant is generally paid on the first drawdown for a contract to build.
On this page11 sections
- Progress payments release a construction loan in stages, as each part of the build is finished
- Queensland contract stages beside one lender's drawdown schedule
- Queensland caps the builder's deposit and ties every claim to work done on site
- From builder's claim to lender drawdown, step by step
- What you pay during the build: usually interest only, on the amount drawn so far
- Some lenders use your own money before the first drawdown
- What can delay a progress payment: a checklist
- If the build goes over budget, tell your lender before you commit
- Practical completion and the final drawdown need extra paperwork
- Applied for through a lender, the Queensland first home owner grant is generally paid at the first drawdown
- Working with a broker on a construction loan
Progress payments release a construction loan in stages, as each part of the build is finished
A construction loan is paid out to your builder in instalments as the build reaches agreed stages, rather than in full on one day. NAB describes it plainly: the lender releases the funds in stages as construction progresses, known as progressive drawdown, and these payments are also called progress payments. A standard home loan, by contrast, is paid out in full at settlement. The payment schedule itself comes from your building contract, and in Queensland the contract sits inside rules administered by the Queensland Building and Construction Commission (QBCC).
Three parties touch every payment: your builder, who claims for a finished stage; you, as the owner who signed the contract; and your lender, which checks the claim and releases the money. This guide follows a payment through all three, using the QBCC's standard new home contract and the published processes of three lenders as examples. It is general information about how progress payments work, not advice on whether a particular loan or contract suits you. How construction lending fits together overall, from pre-approval to the first drawdown, is on FundUp's construction loans page.
Queensland contract stages beside one lender's drawdown schedule
The QBCC New Home Construction Contract gives five default payment stages after a 5% deposit, and each stage is defined by what must be finished before the builder can claim it. Lenders publish their own indicative schedules. The table sets the QBCC template's Option A percentages beside the ranges in ANZ's construction loan handbook, which uses the name lock-up for the stage the QBCC calls Enclosed.
| Stage | What must be finished (QBCC definition, summarised) | QBCC template | ANZ indicative range |
|---|---|---|---|
| Deposit | Paid on signing, before work starts | 5% | 5% |
| Base | Footings, slab, stumps or flooring (as the design requires) completed ready for the walls to go up | 15% | 10% to 20% |
| Frame | Building frame completed and ready for inspection by the certifier | 20% | 15% to 20% |
| Enclosed (lock-up) | External wall cladding and roof fixed, structural flooring laid, external doors fixed | 25% | 20% to 40% |
| Fixing | Internal linings, architraves, cornices, skirting, internal doors, wet area tiling and built-in cabinets fitted | 20% | 20% to 30% |
| Practical completion | Work finished apart from minor defects or omissions | 15% | 10% |
The template's stage payments plus the deposit must add up to the contract price. Where the standard stages do not fit the job, the same schedule has an Option B for the builder and owner to write their own. ANZ's handbook describes six payments in all, with the builder requesting payment on completion of each stage. Its stages do not match the QBCC definitions exactly: ANZ's fixing stage is when plumbing and electrical, including lights and power points, are installed, and its final stage is when painting, cabinetry, tiling and lighting are completed. Read the ANZ column as ANZ's own stages, not the QBCC's. A lender works from the schedule in your signed contract, so it is worth reading that schedule before you sign rather than after the first claim arrives.
Queensland caps the builder's deposit and ties every claim to work done on site
Before work starts, a Queensland builder can usually ask for a deposit of no more than 5% on a contract price of $20,000 or more. The QBCC Consumer Building Guide, in the version effective October 2026, sets the usual maximum at 5% for a contract price of $20,000 or more, the band a new home build falls in, and 20% if more than half the value of the work will be done off-site. The guide notes that domestic building contracts should follow Schedule 1B of the Queensland Building and Construction Commission Act 1991.
After the deposit, the rule is proportion. The QBCC says progress payments should always match the actual work completed and be clearly set out in your contract, and gives a simple test: you should not be asked to pay 50% of the contract price until at least half of the work is done. Payments can be set by construction stage or sometimes at regular intervals such as monthly, in which case the contractor must provide evidence of the value of work done in that period. The QBCC contract schedule carries a warning to owners as well: your cover under the Queensland Home Warranty Scheme may be reduced if you pay more than, or earlier than, the contract requires.
From builder's claim to lender drawdown, step by step
Each progress payment starts with a claim from your builder and ends with your lender paying the builder directly from the loan. The order below follows the QBCC New Home Construction Contract on the owner's side, and the published processes of NAB and ANZ on the lender's side. Other lenders use their own forms and timeframes.
- The builder reaches a stage and issues a claim. Under the QBCC contract the claim must come with any certificates of inspection relevant to that payment stage.
- You check it against the contract. The QBCC contract's owner checklist says to check that the timing and amount agree with the payment schedule, then pay a valid claim within 5 business days of receipt. The practical completion claim is the exception, covered below.
- You dispute it in writing if it is wrong. An owner who disputes a claim, or part of one, gives the builder a QBCC Form 4 Notice of Dispute of Progress Claim, or a similar written notice, within the same 5 business days.
- You send the claim and invoice to your lender. ANZ asks for the builder's invoice and a signed Progress Payment Instruction form. NAB asks for the progress claim and the builder's invoices, and says invoices are required before any claim relating to them can be processed.
- The lender may inspect or value the work. NAB values a registered builder's project before building starts and again at the first and final progress claims, for its own purposes, to confirm it can release more funds. ANZ says its valuers may inspect during different stages and at completion.
- The lender pays the builder. NAB names your builder as the party paid once it receives the claim and invoices.
Timing is where the two sides can pull against each other. For progress claims other than the practical completion claim, the QBCC contract gives the owner 5 business days to pay a valid claim, while ANZ says its progress payment team needs 7 to 10 days to process a request and asks borrowers to send it in as early as possible. Talking to your builder and lender before the first claim about how long each step takes can save a late payment later.
What you pay during the build: usually interest only, on the amount drawn so far
While the home is being built, repayments are usually interest only and are charged on the drawn balance, not the full loan limit. ANZ says you only pay interest on the money drawn down during construction, not the whole amount, and that repayments start once the first progress payment is made to your builder. NAB likewise charges interest only on the amount drawn so far. ANZ calculates interest daily on the balance owing and charges it monthly.
Because each drawdown adds to the balance, the monthly repayment climbs through the build. ANZ notes that the monthly repayment will increase as funds are drawn down, and Westpac says interest payments gradually increase as the lender releases money to pay the builder's invoices. At the end, repayments change again. ANZ says they switch to the terms in your letter of offer, usually principal and interest, which will likely be higher than the interest-only repayments made during the build. NAB says the loan becomes principal and interest once its interest-only period ends, and that you can ask to change over earlier if the build finishes first. How the end of an interest-only period changes repayments is covered in interest-only home loans.
Two practical points follow. Budget for a rising repayment rather than the small first one, especially if you are also paying rent while you build. And check how your loan handles extra money: ANZ, for example, says redraw is not available while you are building.
Some lenders use your own money before the first drawdown
If you are putting your own savings into the build, a lender may require that money to be paid to the builder before the loan starts paying. ANZ says any cash contribution of your own is used first, before it makes the initial drawdown, and that savings put towards the project are paid directly to your builder before you can start using the construction loan. With a lender that works this way, your savings pay the builder's claims first and the loan takes over after that.
The size of that contribution depends on the whole project. NAB notes that buying land and building usually means two deposits, one for the land and one for the build. Lenders look at the expected value of the finished home: NAB estimates the value of the land and the planned build together before building starts, and ANZ arranges a tentative on completion valuation once there are building plans and a contract, to confirm the projected value of the new home. How lenders value property is explained in bank valuations, and what a small deposit means for insurance costs is in lenders mortgage insurance explained. Under the QBCC contract you also give the builder written evidence of your capacity to pay the contract price by the finance date set in the contract.
What can delay a progress payment: a checklist
QBCC and lender material points to four kinds of hold-up: missing paperwork, an inspection, a change to the work, or a cost the loan does not cover. These are the specific causes they name, with the step that helps avoid each one:
- No invoice, or the wrong one. NAB will not process a claim until the related invoices arrive. Ask the builder for the invoice with every claim.
- Insurance not supplied. NAB requires copies of insurance policies, such as builders all risk, home warranty and public liability insurance, before the first progress payment.
- A lender inspection. NAB inspects at the first and final claims, and ANZ's valuers may inspect at other stages. Allow time for access to the site.
- Processing time. ANZ allows 7 to 10 days to process a request; send each one as soon as the claim is checked.
- A claim that runs ahead of the work. If the amount claimed is more than the work on site, the QBCC says payments should match the work actually completed. Dispute it in writing within 5 business days.
- A variation without paperwork. The QBCC describes a variation as a change to the materials, scope or work in your contract and says to agree every variation in writing before the work begins. Under the QBCC contract, a price increase from a variation cannot be required to be paid before that work is completed.
- A cost overrun. NAB describes this as building costs going above the progress payments agreed at the start of the loan, such as switching cladding from timber to brick. Westpac says cost increases usually need credit approval and may need a revised valuation, which can bring extra fees or a lower loan limit.
- Lender time limits. ANZ requires the first progress payment request within 6 months of the signed letter of offer and the build to finish within 24 months of the first drawdown, after which remaining funds may not be available.
If the build goes over budget, tell your lender before you commit
Lenders treat extra costs during the build as a change to the loan agreed at the start, so they are not simply added to it. ANZ's handbook gives one lender's rule: if an invoice creates a shortfall of less than $5,000 for the rest of the build, ANZ may cover it during construction, but you repay it at the end; above $5,000 you use your savings to cover the difference. NAB asks borrowers to contact it right away when a cost overrun happens so it can talk through options, and Westpac recommends speaking to your lender before committing to any cost change. Agreeing each variation in writing before the work begins, as the QBCC advises, means its cost is known before it reaches a progress claim.
Practical completion and the final drawdown need extra paperwork
The last progress payment is released only once the home is finished and both the contract and the lender's completion requirements are met. The QBCC guide says you do not have to make the final contract payment until the work is completed. Under the QBCC contract the builder gives you 5 business days' written notice of the expected practical completion date, and the practical completion claim must come with a signed Form 6 Defects Document and a Form 7 Certificate of Practical Completion, or similar documents. The 5 business day window for other claims does not apply here: once the builder has met those handover requirements, the contract says the owner must pay the practical completion claim immediately, so your lender's processing time matters most at this stage.
Lenders add their own conditions to the final drawdown. NAB asks for a copy of the occupancy certificate or interim occupancy certificate for a new home, and may ask for the building insurance policy. ANZ must confirm the house is insured before making the final payment, and asks for the building insurance certificate of currency and a certificate of occupancy where your state requires one. Westpac says the final payment may depend on a satisfactory final inspection by the lender's valuer, confirming the home was built to the original plans and specifications. The QBCC contract's own checklist tells owners to liaise with their lender as practical completion approaches so the final payment is ready on time.
Applied for through a lender, the Queensland first home owner grant is generally paid at the first drawdown
For an eligible first home buyer building under a contract and applying through a bank or lender, the Queensland Revenue Office says the grant is generally paid on the first drawdown of funds. If you apply directly to QRO instead, the grant is not paid until the home is complete and all supporting documents are supplied. QRO advises against counting on the grant as a deposit because the payment date varies.
Variations matter here too. If the grant was paid before completion, QRO says you must tell it within 28 days if the value of the new home reaches $750,000 or more, including contract variations. Eligibility, amounts and the cap are covered in the Queensland first home owner grant guide, and first home duty concessions are covered in stamp duty in Queensland.
Working with a broker on a construction loan
Lenders differ on construction stages, inspections, processing times and how they treat cost overruns, so the same build can run differently depending on the loan. FundUp is a Cairns-based mortgage broker that compares 40+ lenders and lends Australia-wide, with suburb guides for Cairns and the northern beaches. Its construction loans page says FundUp helps manage each drawdown so your builder is paid on time, stage by stage. The service is free to you; the lender pays a commission when your loan settles. No lender's approval or payment timing can be promised in advance: each lender applies its own assessment and conditions. You can call 0412 885 734.
Frequently asked questions
How many progress payments are there on a construction loan?
It depends on your building contract. The QBCC New Home Construction Contract uses a 5% deposit and five stages: Base, Frame, Enclosed, Fixing and Practical Completion, which makes six payments in all. ANZ's handbook also describes six. The QBCC contract lets the builder and owner set different stages where the standard ones do not suit the job, so check the payment schedule in your contract before you sign.
Do I pay interest on the full construction loan amount?
Usually not during the build. Lenders such as NAB and ANZ charge interest only on the amount drawn so far, so repayments start once the first progress payment is made and rise with each drawdown. Once construction finishes, or the interest-only period ends, the loan generally switches to principal and interest repayments, which are likely to be higher than the repayments during the build.
What happens if my build goes over budget?
Extra costs are not automatically added to the loan. Westpac says cost increases usually need credit approval and may need a revised valuation, which can bring extra fees or a lower loan limit. ANZ may cover a shortfall under $5,000 during construction, repaid at the end, and expects you to use savings above that. Agree every variation in writing before the work starts, and tell your lender early.
Who approves each progress payment?
Both you and your lender check each claim, for different reasons. Under the QBCC contract you check the claim against the payment schedule and pay a valid progress claim within 5 business days, or dispute it in writing; the practical completion claim is due once the builder meets the handover requirements. The lender then checks the invoice and may inspect the work before releasing funds to the builder. NAB, for example, says its inspections are for its own internal purposes.
When is the Queensland first home owner grant paid on a build?
When you apply through a bank or lender for a contract to build, the Queensland Revenue Office says the grant is generally paid on the first drawdown of funds. If you apply directly to the Queensland Revenue Office, it is not paid until the home is complete and every supporting document is supplied. The Revenue Office advises against relying on the grant as a deposit because the payment date varies.
Can a Cairns broker help with a construction loan?
Yes. FundUp is a Cairns-based mortgage broker that compares 40+ lenders and lends Australia-wide. Because lenders differ on stages, inspections, processing times and cost overruns, a broker can compare how each lender handles a build before you apply. FundUp's construction loans page says it helps manage each drawdown so the builder is paid on time. The service is free to you, as the lender pays a commission when the loan settles.
Sources
8 published sources, 5 from government and regulators. Each was checked on the date shown.
Government and regulators5
- Consumer Building Guide for Home Owners (effective October 2026)Queensland Building and Construction Commission, accessed accessed (opens in a new tab)
- Understanding deposits and progress paymentsQueensland Building and Construction Commission, accessed accessed (opens in a new tab)
- Schedule for QBCC New Home Construction Contract (July 2023)Queensland Building and Construction Commission, accessed accessed (opens in a new tab)
- QBCC New Home Construction Contract General Conditions (July 2023)Queensland Building and Construction Commission, accessed accessed (opens in a new tab)
- First home owner grant payment and obligationsQueensland Revenue Office, accessed accessed (opens in a new tab)
About this guide
- Published
- Written by
- FundUp
This guide is general information only. It does not take into account your objectives, financial situation or needs, and it is not a recommendation of any lender or product. Lender policies change; check the current position with a broker or the lender before acting.
Loan Ranger Finance Pty Ltd Trading as FundUp is a Credit Representative 571356 of LMG Broker Services Pty Ltd ACN 632 405 504 Australian Credit Licence 517192.
Next steps
Want this worked out for your situation?
A broker can check which lenders' policies fit your income, deposit and property.